By Andrew
Buchanan
It is generally accepted within the Insurance Industry that, all else
being equal, claims grow more expensive with age. Technical arguments always have their place
but the bottom-line is that such arguments must always be justified by saving
more than they cost to run. The pragmatic approach can often result in less
overall expenditure, as illustrated by the following two cases recently adjusted
by me.
In the first case, my Principals Insured were Scrap Metal Merchants who
had a permanent presence on a Steelworks site owned and operated by a third
party. The Insured controlled a large
stock-pile of scrap steel, when they would deposit into vehicles operated by
various third-party hauliers using a crane-grab. An accident occurred when a piece of steel
fell from the stockpile and struck a third-party driver, resulting in him sustaining
a fractured spine.
The accident was caused by a combination of the stock-pile being too
high and a failure to ensure that drivers stayed away from the “danger zone”
during the loading operation. The
Insured, as the party in ultimate control of the stockpile, had a clear
liability. The Site Owners also had a
liability due to their failure to instruct and direct third-party drivers
entering the site. The Haulier also had
a liability given they had not adequately trained/instructed their drivers .
Prior to litigation commencing, I wrote to the Opposing Insurers
recommending that liability be shared between the three Insureds/Defendants,
but neither Opposing Insurer was willing to compromise and admit even partial
responsibility.
In the absence of agreement, the case litigated and I immediately instructed
a firm of Solicitors. By co-incidence
the two Opposing Adjusters (without realising) also sent instructions to the
same law firm. The Solicitors quickly
identified the conflict of interest and sought my instructions.
Having been the first to instruct, I had the opportunity to tell the
Solicitors to cease acting for the other two Defendants, whose Insurers would
then have to appoint alternative Solicitors.
Instead I proposed that I would permit the Solicitors to continue to act
for all three Insurers provided that agreement could be reached on liability
apportionment between the three Defendants within a fortnight.
As a result, a one-third/one-third/one-third share was agreed between
the three Defendants/their Insurers within one-month of litigation
commencing. This prompt agreement, which in turn enabled swift
settlement of the claim, resulted in a significant saving in Solicitors’ Costs
(both Defendants’ and Claimant’s).
It is strange (and unfortunate) that such a pragmatic solution could not
have been reached prior to litigation, and it is highly unlikely that it would
have happened for some time had three different firms of Solicitors been
appointed. Had the case gone to Court,
it is probable that at least one of the parties would have been held to
contribute less than one-third, but that would clearly have been a pyrrhic
victory.
The second example involved a Products Liability claim relating to the
supply of game-bird feed. The feed (which
was produced on a bespoke basis for the Claimant) was allegedly defective,
resulting in the birds rejecting it, which caused them to become
under-nourished, allowing disease to set in and thousands of birds to die.
Aside from numerous issues regarding whether the feed was indeed
defective and whether it was causative of the birds’ deaths, a significant
problem arose due to the Insured having changed Insurer at the worst possible
time: the preceding Insurer had been on cover when the Product was supplied to
the Claimant and he had first started to feed such to his birds, but their
cover terminated (and my Principal’s began) prior to the birds starting to die
in significant numbers.
The Operative Clause of both Policies was written on a “Damage
Occurring” basis, but when did the damage occur: when the birds started to
reject the feed (and started to become malnourished)? At the point when they
actually became medically “malnourished” and required veterinary treatment? When death occurred?
Clearly no loss or damage occurred straight-away: it would take some
time for the lack of food to have a negative impact on the birds’
health/development. Conversely, it is
clear that the birds had sustained “damage” (even if their malnourishment was
treatable, their development would have been set back) prior to their
deaths. The situation was further complicated by the
fact that the affected birds numbered in the tens of thousands and the “occurrence”
date would differ between birds.
So what should the percentage split be between the two Insurers? There was, quite simply, no precise answer on
the available evidence. Both Insurers
could bring to bear justifiable arguments that the other should contribute the
lion’s share.
However, it was recognised that
the increased legal costs resulting from delay would likely exceed the savings
available and both Insurers were persuaded to agree a 50:50% proportionate
share of all outlays.
This spirit of pragmatic
compromise extended to both the Insured and Claimant. Through open discussion it was recognised
that the Insured, who had raised debt-recovery proceedings against the
Claimant, would be happy to have their outstanding debt (owed by the Claimant
for unpaid feed) cleared and that the Claimant would be willing to walk away
from his claim in the event the debt was written off: this being a fraction of
the sum claimed (as supported by Veterinary Reports).
Ultimately, both the
Insured and Claimant seemingly walked away happy with the outcome and each Insurer’s
total outlays measured just into five-figure sums (when the potential combined
claim value, inclusive of litigation costs had been approaching six-figures).
At Technical Assessing,
we often say that our aim is to settle claims for the “right amount”, but the
right amount must always take into account cost implications. Our aim to settle claims quickly and
pro-actively with the aim of avoiding unnecessary legal dispute and associated
cost.
No comments:
Post a Comment